The build, day by day
Corporate HQ · 6,400 sq ft · Sector 62
An empty floor in January. Ninety-six people working in it 70 days later, without losing a working day.
Empty floor survey
Floor measured, services mapped, building NOCs filed.
Booking · 10%MEP & partitions
HVAC, fire and electrical routed; cabin partitions framed.
Stage 1 · 25%Ceilings & glazing
Acoustic ceilings, glass fronts and door frames installed.
Stage 2 · 20%Joinery & reception
Reception desk, storage walls and boardroom joinery fitted.
Stage 3 · 20%Flooring & paint
Carpet tiles, feature paint and branded wall graphics.
Stage 4 · 15%Furniture & IT
Workstations, chairs, AV and network commissioning.
Stage 5 · 8%Handover
Snags cleared, as-built drawings and warranty to facilities.
Final · 2%